Lesson 6, module 2: Projects, tasks and team Tasks, their statuses and the team's workload Who's doing what this week, and who's already swamped?
A complete task can be picked up without asking questions. Actionable title, priority, due date Estimated hours, assignees Planned branch and source Four statuses, and a person to close. [Diagram: The life of a task] 1. To do 2. In progress 3. In review 4. Done Four statuses. Moving to "In review" calls for a person; only that review closes the task. The agent breaks down the brief, you approve before it creates. Request: Break the wine merchant's brief into tasks for three weeks: title, priority, due date, hours, likely person. Don't create anything before I agree. Answer: A list of proposed tasks in the chat, with the requested fields and the open questions. They're only created after you approve. Urgent stays rare: two questions are enough to choose. [Diagram: Choosing a task's priority] Vertically, impact on the client or the site; horizontally, due date. High Low Normal Preferred: Urgent Two questions: is the due date close, is the client or the site affected? Urgent stays rare. The team's workload, then the plan: you decide. Delays and due dates per member Estimated hours, unassigned tasks Absences read from Pilote and Agenda In the exercise, you set up the tasks for the wine merchant's website.
Your turn: The wine merchant's website tasks The written lesson, the worked exercise and the quiz are below the video.
Lesson 6 of 48 · module 2, projects, tasks and team
Tasks, their statuses and the team’s workload
A Nexus task has an actionable title, a priority, a deadline, an estimated duration in hours, assignees, a planned branch and its source. It moves from To do to In progress, In review and then Done. The team’s workload shows, member by member, overdue tasks, deadlines and estimated hours; the agent turns this into a weekly plan that you decide on.
20 min of reading
1 min 45 of video
6 diagrams
4 demandes to copy
3 exemples pratiques
4 exercices answerss
5 questions
1 ressource
By the end of this lesson, you will know how to
Create complete tasks and have the agent break down a brief, after approval
Track progress with statuses, the board or list view and the nexus taches command
Read the team’s workload and decide on the weekly plan proposed by the agent
What’s covered
What a task holds
Create tasks by hand or through the agent
Statuses and tracking
The right priority
The team workload and the week’s plan
3 worked examples, followed from start to finish
Exercise with answers · The wine merchant’s website tasks
3 practice exercises, from guided to demanding cases
The quiz
Key points
A complete task has an actionable title, criteria, a priority, a deadline, hours, an assignee, a branch and its source.
Four statuses: To do, In progress, In review, Done; a person closes the task.
The agent proposes a breakdown of a brief and waits for your approval before creating anything.
A task without an estimate counts as zero hours: fill it in before reading the workload.
“Organise the week” gives you a plan; assignments remain your decision.
Monday, 8.30am. The wine merchant’s brief is in the project record and the conventions are written down. Claire now has to turn four pages of brief into work shared between Malik, Inès and Théo, knowing that Inès is on leave on Thursday and Friday and Malik is finishing another website. Tasks are where the project becomes a schedule, and where each agent gets its context.
What a task holds
The fields of a task, as at 15/11/2026
Field
What it says
Example for the wine merchant
Title
A verb and an object, actionable
“Build the home page from the final mock-up”
Description
What needs doing, the acceptance criteria, the known pitfalls
“No prices; photo of the winery in the snow above the fold”
Priority
Low, normal, high, urgent
High
Due date
The expected date
Wednesday 18 November
Estimated duration
In whole hours
6 heures
Assignees
One or more people; assigning adds the person to the project
Malik
Planned branch
The git branch where the work will be done
page-accueil
Source
The link to the item that gave rise to the task
The link to Sandrine’s e-mail or request
Attachments
The documents needed for the task
The wine list
A well-filled task can be picked up without a meeting: the colleague who opens it, or the agent launched via “Work on it”, finds the goal, the criteria, the branch and the origin. Discussions and changes stay attached to the task until review. The source is often neglected: it’s what lets you reread the client’s exact words weeks later.
Create tasks by hand or through the agent
Create a task in the Tasks app
Open Tasks from the dock; choose the Board or List view, and the columns to display.
Create a task in the wine merchant’s project; give it a title that starts with a verb.
Fill in the description with the acceptance criteria, then the priority, deadline and duration in hours.
Assign Malik; add the planned branch and paste the link to the source.
The label may vary slightly between versions: if a field doesn’t appear, look for it in the task details rather than in the table row.
Have the brief broken down into tasks
Read the project record and brief.
Propose a breakdown into tasks for the next three weeks, with go-live on Tuesday 24 November.
For each task: a title starting with a verb, a description with acceptance criteria, priority, deadline, estimated duration in hours, the intended person (Malik for code, Inès for design, Théo for copy and communication), and the planned branch for code tasks.
Inès is away on Thursday 19 and Friday 20 November.
Don’t create anything until I agree.
Roughly what you should get
A table of around fifteen tasks in the conversation, in working order, with the requested fields. The agent flags what the brief doesn’t let it estimate (the volume of English copy, for example). The tasks are only created after your reply.
Nexus is designed this way: the agent has the breakdown approved before creating anything, unless you yourself told it to create the tasks.
Create after correction
Your breakdown works for me, with three changes: task 4 moves to urgent priority, task 9 is assigned to Théo, task 12 goes from 10 to 6 hours.
Create the tasks in this order, then give me the list with their links.
Roughly what you should get
The tasks created in the project, with the status To do, and a list of them with a nexus://tache/… link for each.
Statuses and tracking
The life of a task
1To do
Created, with priority, due date, estimated duration and assignee.
2In progress
Someone, or an agent via “Work on it”, has started on it.
3In review
The work is handed in; a person reviews it.
4Completed
Reviewed and accepted. The history stays attached to the task.
Four statuses. Moving to “In review” calls for a person; only their review closes the task.
The statuses are shown as To do, In progress, In review and Done (their internal values are TODO, IN_PROGRESS, IN_REVIEW, DONE). One simple rule keeps the team on track: an agent can move a task to review, a person closes it. On the web app home page, the “My tasks in progress” section shows each task’s status, its deadline or the note “N days overdue”, with “Add a deadline” when there isn’t one.
Tracking tasks from the terminalTerminal
# Vos tâches
nexus taches
# Les tâches de tous, sur un projet (le point désigne le projet du dossier courant)
nexus taches --toutes --projet "Négociant Saint-Émilion"
nexus taches --projet .
# Seulement ce qui attend une relecture (valeurs : TODO, IN_PROGRESS, IN_REVIEW, DONE)
nexus taches --toutes --statut IN_REVIEW
# Pour un script : chaque tâche avec id, titre, statut, projet, affectés, échéance, lien
nexus taches --toutes --json
Read-only commands, tested on 15 November 2026 with version 0.11.69.
The right priority
Choose a task’s priority
fortImpact on the client or the sitefaible
High
High impact, distant due date: the home page mock-up three weeks out.
Urgent
High impact, close due date: the broken contact form.
Low
Low impact, nothing pressing: renaming images.
Normal
Low impact, close due date: the Legal notice page to review.
lointaineDue dateproche
Two questions: is the due date close, and is the client or the site affected? Urgent stays rare.
The team workload and the week’s plan
The team workload shows, for each active member, their tasks that are overdue, due within the period and in progress, their estimated hours and what has no estimate. A member with no workload appears too: that is free capacity. Unassigned tasks are listed separately. By default, the period is the working week; on Friday and at the weekend, it is the following week. It is read with your permissions: a developer only sees the projects they belong to.
Organise the week
Organise the week for the studio team.
Start from the team’s workload, then check absences and leave in Pilote and appointments in Agenda.
Propose a day-by-day plan: who does which task, with estimated hours, and flag overloads, tasks without estimates and tasks without an assignee.
Don’t change any assignments: I’ll decide.
Roughly what you should get
A plan by day and by person, then three short lists: overloads (for example Malik at 46 estimated hours for a 35-hour week), tasks without estimates, tasks without an assignee. Assignments stay as they are until you decide.
3 SME situations followed from start to finish: the prompts exactly as they were written, the model answer to aim for, and what was checked before sending.
Example 1
A two-person agency and its back-to-work week
Benoît and Laura run a small two-person website design agency in Pessac. On the Monday back in January, seven clients have written over the holidays, and no task has an estimate. They want to know whether they’ll get through the week.
Back-to-work Monday
1No estimate
Eleven tasks at zero hours.
2Proposals
Based on comparable tasks.
3Approval
Four estimates corrected.
4Plan
One overload spotted, two tasks moved.
Request 1
List the open tasks in our projects that have no estimated duration or no assignee. For each one, propose an estimate in hours and a person, based on comparable tasks already completed. Don’t change anything.
Model answer
Eleven tasks without estimates, three without an assignee. For each one: a proposed estimate (for example “Fix the florist’s website mobile menu, 2 hours, based on a comparable task completed in November”) and a person. Two tasks have no equivalent: you’ll need to estimate those yourself.
Benoît corrects four estimates and approves the rest.
Request 2
Apply the approved estimates and assignments, then organise the week for the two of us, 32 hours each, and flag anything that doesn’t fit.
Model answer
A day-by-day plan. Laura reaches 38 hours: two low-priority tasks are proposed for the following week. Benoît stays at 29 hours.
Laura postpones the two low-priority tasks and lets the two clients concerned know.
What was checked before sending
No estimate was applied without Benoît’s review.
The workload reviewed after updating, with no zero-hour tasks.
Clients whose work is moved are told by Laura, not by the agent.
Rough scale: an hour of Monday sorting cut to twenty minutes, and an overload spotted on Monday rather than Thursday.
Example 2
A signage workshop that tracks its jobs
Fabrice is workshop manager at a 22-employee signage and shop-sign company in Bègles. He runs each order as a project: mock-up, client approval, manufacture, installation. The fitters don’t code and check their tasks on the web.
A sign, from mock-up to fitting
MondayMock-up
Three hours, graphic designer.
TuesdayApproval
The client’s e-mail as the source.
WednesdayBreakdown
Four hours, workshop.
ThursdayFitting
Two fitters, aerial platform booked.
Request 1
For the Gradignan pharmacy sign order, create the following tasks after reviewing them with me: mock-up (the graphic designer, 3 hours), client approval (source: their e-mail), cutting (workshop, 4 hours), fitting (two fitters, 5 hours, Thursday). First propose the text of each task.
Model answer
Four tasks proposed, with title, description, priority, deadline and hours. The client approval has the e-mail link as its source. The fitting has two assignees.
Fabrice adds to the installation task: “aerial platform booked, check the weather the day before”.
Request 2
Create the four tasks. Then show me the workshop’s workload for next week.
Model answer
The four tasks created. The workshop’s workload: the two fitters at 31 and 34 hours; an unassigned cutting task from another order.
He assigns the unassigned breakdown task himself.
What was checked before sending
Every task has a duration in hours and an assignee, except the unassigned one identified.
The source of the approval is the client’s e-mail, which can be retrieved.
The fitters see their tasks in “My tasks in progress” on the web.
Rough scale: the workshop’s roadmap kept up in ten minutes per order, instead of a whiteboard copied out every Monday.
Example 3
A sports club and its volunteers
Hélène coordinates an amateur rugby club with 300 registered players in Libourne, with two employees and about twenty volunteers. She is preparing the youth tournament on 15 March and wants everyone to know what they have to do, without a weekly meeting.
Before and after the tasks
Before
A meeting every Monday
A paper chart in the clubhouse
Delays discovered late
After
Fourteen dated tasks
The list of overdue tasks on Monday
Two targeted calls
Request 1
Break down the preparation of the 15 March tournament into tasks: refreshment bar, referees, pitches, accommodation for visiting teams, communication. For each: title, due date, hours, likely person from the two employees. Don’t create anything until I agree.
Model answer
Fourteen tasks proposed, in five sections, with deadlines counting back from 15 March (pitch booking at D-45, referee list at D-30, refreshment stand order at D-10). Three tasks with no obvious owner are flagged.
Hélène approves, assigns two tasks to volunteers who are members of the workspace, and keeps the third for herself.
Request 2
Every Monday, I want to know what’s overdue. List the tournament tasks that are overdue or due this week, with the assignee.
Model answer
A short list, sorted by deadline, showing how many days overdue where applicable.
She uses this list to call only the two people concerned.
What was checked before sending
The deadlines are consistent with the tournament date, checked by Hélène.
The assigned volunteers are members of the workspace and can see their tasks.
No assignment made by the agent without their agreement.
Rough scale: a one-hour weekly meeting replaced by two targeted ten-minute calls.
Here is what Claire knows on Monday 16 November: the site goes live on Tuesday 24 November; the home page mock-up is approved, those for the Our wines and The cellar pages are to be approved by Inès on Wednesday; the English copy needs reviewing by Sandrine’s importer; Inès is away on Thursday 19 and Friday 20; Malik is finishing another website until Tuesday evening; Théo is available all week; the old site’s contact form has stopped working since this morning, according to an e-mail from Sandrine. Write eight complete tasks (title, priority, deadline, hours, assignee, branch if code, source), then spot the main risk of the week.
Start with the task that Sandrine’s e-mail makes urgent.
Schedule Inès’s tasks before her absence.
Don’t give Malik any code tasks before Wednesday.
Give every task an estimated duration, even a rough one.
Spot the risk that threatens the 24 November go-live.
See the answers
Task
Priority
Due date
Hours
Assignee
Restore the old site’s contact form (source: Sandrine’s e-mail)
Urgent
Monday 17
2
Malik
Approve the Our wines and The cellar mock-ups
High
Wednesday 19
4
Inès
Write the French copy for the six pages
High
Wednesday 19
8
Théo
Have the importer review the English texts
High
Monday 24
2
Théo
Build the home page (branch page-accueil)
High
Friday 20
6
Malik
Build Our wines and The winery (branch pages-vins-chai)
High
Tuesday 25
10
Malik
Prepare the cellar photos for the web
Normal
Wednesday 19
3
Inès
Full acceptance test in pre-production
High
Wednesday 26
4
Claire
The urgent task is the only exception to the rule about Malik: a contact form down in production affects the client today. It is worth two hours, not a day. The main risk of the week is the importer’s review: it depends on an outside person, with no guaranteed due date. Schedule it early, and plan to deliver in French only if the English isn’t reviewed in time, with Sandrine’s agreement.
Have the agent check the plan
Here are the eight tasks I plan to create: [paste the table].
Check them against the team’s workload this week: does anyone go over 35 hours? Does any task fall during someone’s absence? Don’t create anything.
Roughly what you should get
A short answer: any overruns, by person, and any tasks that fall during Inès’s absence.
Practise
Three more exercises, from the most guided to the most demanding. The material is provided in full: copy it into your tool, then check your work against the criteria before opening the answers.
Level 1 · guided10 min
Titles that read as actions
Rewrite each task title so that it starts with a verb and states the object, then give each one a priority using the matrix from the lesson.
At most one task is urgent, and the reason is given
See the answers
“Restore contact form submission”: urgent if it is down in production, otherwise high.
“Propose three logo options based on the approved brand territory”: high.
“Prepare the winery photos for the web”: normal.
“Review the legal notice with Sandrine”: normal.
“Fix the cropped photos on the Our wines page on mobile”: high, source Sandrine’s message.
“Prepare the agenda for the kick-off meeting”: normal.
Check what is still waitingTerminal
# Les tâches du projet encore à faire
nexus taches --toutes --projet "Négociant Saint-Émilion" --statut TODO
Level 2 · independent20 min
Monday’s workload
Read the workload extract below. Say what is wrong, what needs filling in before deciding, and write a suitable “Organise the week” request.
The material to work on
Team workload, week of 23 November (extract):
Malik: 2 tasks overdue, 3 due, 41 h estimated, 1 task without an estimate.
Inès: 0 overdue, 2 due, 9 h estimated, 4 tasks without an estimate.
Théo: 0 overdue, 1 due, 6 h estimated, 0 without an estimate.
Claire: 1 overdue, 2 due, 18 h estimated.
Unassigned tasks: “Prepare full acceptance testing”, “Write the go-live report”.
Reminder: 35-hour week; Théo on a training course Tuesday.
Check your work
Malik’s overload is flagged (41 hours against 35)
Inès’s workload is judged unreliable because of the four tasks without an estimate
The two unassigned tasks are named
The request has absences read from Pilote and appointments from Agenda
The request changes no assignments
See the answers
Malik is six hours over and has two overdue tasks: one task has to go or slip. Inès looks free, but four tasks without estimates make her 9 hours misleading: fill those in first. Théo is the spare capacity, except on Tuesday. Two tasks have no assignee.
The adapted request
Organise the week of 23 November for the team.
First: propose an estimate in hours for Inès’s four tasks and Malik’s one task that don’t have one, based on comparable tasks, and wait for my approval.
Then: read the absences in Pilote and the appointments in Agenda (Théo is on a training course on Tuesday), and propose a day-by-day plan that brings Malik down to 35 hours at most, and suggest a person for the two unassigned tasks.
Don’t change any assignments without my agreement.
Roughly what you should get
First, five proposed estimates; after approval, a day-by-day plan, one of Malik’s tasks offered to Théo, and a proposal for each unassigned task.
Level 3 · demanding case35 min
Getting a project back in order
The project below has drifted. Write the diagnosis, the list of corrections to make to the tasks, the sequence of requests to the agent (in order, each with its limit) and what Claire decides herself.
The material to work on
“Négociant Saint-Émilion” project, Thursday 19 November, go-live on Tuesday 24.
Open tasks: 23.
- 9 tasks at urgent priority.
- 6 tasks without a deadline.
- 5 tasks without an estimated duration.
- 4 tasks in review for more than five days.
- 3 tasks without an assignee, including “Run the full acceptance test”.
- 2 duplicate tasks: “Build home page” and “Home page build”.
- 1 task “Fix form” with no source or description.
Sandrine’s e-mail this morning: she agrees to deliver the English on 5 December.
Check your work
The diagnosis links the nine urgent tasks to a lost sense of priority
Tasks that have been in review for five days are dealt with first by a person
The duplicate is merged, keeping the history of the more advanced task
Moving the English to 5 December changes deadlines, with the e-mail as the source
Every request to the agent says what it must not do
See the answers
Diagnosis: priority no longer sorts anything (9 urgent tasks), the workload is wrong (5 without an estimate), review is a bottleneck (4 in review), and nobody owns acceptance testing.
Claire reviews the four tasks in review herself and closes them or sends them back.
Claire assigns herself “Prepare full acceptance testing”.
The agent proposes; Claire approves: recalculated priorities, due dates, estimates, merging of the duplicate.
The English tasks move to 5 December, with Sandrine’s e-mail as the source.
The first request to restore order
In the wine merchant’s project, propose without changing anything:
1. a new priority for each of the 9 urgent tasks, using the rule “urgent only if the live site or the client is affected before Friday”;
2. a due date for the 6 tasks that have none, before 24 November, except the English ones, set for 5 December (source: Sandrine’s e-mail this morning);
3. a duration in hours for the 5 tasks without an estimate;
4. which of the two home page tasks to keep: the one with the most advanced history.
A table, then wait for my approval.
Roughly what you should get
A table in four parts, with the reason for each proposal. Nothing is changed before Claire approves.
The task without a source
The “Fix form” task has neither a source nor a description. Search the project’s requests and e-mails for what may have prompted it, and propose a description with acceptance criteria. Don’t change the task.
Roughly what you should get
The link to the original message if it is found, and a suggested description; otherwise, a note that no source was found and a question for Claire.
Every request to the project agent written in the course, including model answers, worked examples and practice exercises, sorted by module and lesson, with filters to find the right one.
For each lesson, the main exercise and the three graded practice exercises with their materials, to do on paper or alongside Nexus; all model answers are gathered at the end.
The course’s worked examples, from the first project to production: the situation, the request as it was written, the agent’s typical answer and what was checked before approving.
All the lessons in a single PDF: objectives, written course with its diagrams, tables and requests, common mistakes, exercise and key takeaways. The practice exercises and answers are in the workbook, the examples in the collection.
Your notes stay on this device; they are not sent anywhere.
A question for the tutor
A result that doesn’t match the model answer, a prompt that gets you nowhere, a case specific to your business: write to us with your prompt and the response you got. A Bonbay Académie trainer replies within 24 working hours, on your case.